Currently the Pre-Con Milestone "Pre-Mobilization Complete: Ready to Start/Mobilization Checklist Complete" is synced with the Global Milestone in the Construction Schedule "Mobilization Start: Acceptance of RTS"
The Sync will be broken if:
- The Construction Milestone is moved to a later date manually
- A Construction Schedule is made Active
- The Pre-Con Milestone is given a Status of Complete
- The Construction Schedule is made active (Only on a BOOL project)
Note: When the dates on the two milestones become out of sync an error message will appear that reads, "Pre-Con and Construction Ready To Start milestones are un-synced. Move the pre-con RTS to the same or later date as the construction RTS to re-sync."